Extension of time - approval letter example
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).
When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay.
A formal letter is addressed to the contract administrator requesting the extension of time, and presenting the reasons for the request. This letter is then evaluated before approval or rejection. If it is approved, the letter is given a written answer by the contract administrator and a change order is issued.
Here is an example of an approval letter:
Contractor's Name Contract Name Contract Number I refer to your extension of time claim dated [insert date of the claim]. In accordance with clause [insert the contract clause] of the General Conditions of Contract, the Principal grants extension/s of time: [Insert number of days requested and reasons for the time extension.] The Contractual Completion Date (as previously extended) was [insert contract completion date including previous time extension approvals]. This extension of [number of days] days makes [insert new completion date] the Contractual Completion Date. Signed by, Authorised Person |
[edit] Related articles on Designing Buildings
- Acceleration of construction works.
- Change order.
- Common refusals of extensions of time.
- Compensation event.
- Contract administrator.
- Contract claims.
- Delay damages.
- Extension of time.
- How to prepare a claim for an extension of time.
- Practical completion.
- Project programme.
- Time Risk Allowance TRA.
- Variations.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.